Central Sector Scheme for construction of storage godowns

The Department is implementing the Central Sector Scheme for construction of godowns with focus on augmenting capacity in the North Eastern Region. The scheme is also operative in a few other States like Himachal Pradesh & Kerala. Funds are released to the FCI in the form of equity for land acquisition and for construction of storage godowns and related infrastructure like railway sidings, electrification, installation of weighbridge, etc.

Physical achievement and funds released to FCI during the 12th Plan Period i.e. 2012-13 to 2016-17 are as below:-

Year

North East Region

Other States

Total (NE+Other States)

Physical

(in MT)

Financial

(in Rs Cr)

Physical

(in MT)

Financial

(in Rs Cr)

Physical

(in MT)

Financial

(in Rs Cr)

2012-13

2,910

19.28

-

4.00

2,910

23.28

2013-14

2,500

-

20,000

3.00

22,500

3.00

2014-15

43,480

71.84

-

15.00

43,480

86.84

2015-16

64,810

67.70

-

-

64,810

67.70

2016-17

3,980

35.75

-

-

3,980

35.75

Total

1,17,680

194.57

20,000

22.00

1,37,680

216.57

The scheme would be continued for next three years, i.e. 2017-18 to 2019-20. The projected physical targets and achievements are as given below:

Agency

States

Capacity to be created 2017-20

(in MT)

Capacity created upto October, 2017

(in MT)

FCI

Assam

42500

-

Arunachal PD.

6130

-

Manipur

25000

-

Meghalaya

7500

-

Mizoram

10000

-

Nagaland

4590

4,590

Sikkim

3500

-

Tripura

20000

-

Total NE

119220

4,590

Himachal PD.

11220

-

Kerala

15000

-

Jharkhand

65000

-

Total ONE

91220

-

Total (NE + ONE )

2,10,440

4,590

* Equity of Rs. 12.17 crore has been released to FCI on 28.09.2017 for NE Region.